FIELD REPORT
On-site content
In a limited work space, we used a 13t rough terrain crane to dismantle and transport the tower crane, which had been lowered to near the ground by reverse climbing. Work is completed with emphasis on safety and setup while checking surrounding conditions.
- case number
- 10
- Main contents
- Tower crane dismantling
- Corresponding attitude
- We check site conditions and develop construction methods while considering safety and work efficiency.