Construction consultation

FIELD JOURNAL

Hisatec's work

A record of the techniques and ingenuity accumulated in the field.

HOW WE SOLVE

Create answers for each site in four stages.

Even if the work name is the same, the conditions are different one by one. Construction is carried out after repeated checks and improvements.

  1. CONDITIONread the terms

    Check dimensions, weight, and flow lines

  2. METHODchoose a method

    Optimize equipment and procedures

  3. TEAMwork together

    Share safety information with stakeholders

  4. RESULTbe sure to pay

    Check quality and completion status

OUR WORKS

At each site, the best answer.

From transporting and installing heavy objects to construction under special conditions. You can view all the work and on-site photos posted on the current site in their original size.

shirring
shirring

01

shirring

It was shirring. Western Service helped us with the crane. Although the dismantling method was different from what I had expected, CM's Engineering Co., Ltd. did a great job of disassembling it ^_^ It was able to be removed very smoothly. thank you. Thank you to everyone.

See photos and site details in detail
gondola shakedown
gondola shakedown

02

gondola shakedown

It was a gondola shakedown. Thank you Futaba Giken for your request ^_^ I was able to study on Mr. Daiyu's gondola, and I had time, so I made this. We look forward to receiving your request again.

See photos and site details in detail
35t rough terrain crane
35t rough terrain crane

03

35t rough terrain crane

We worked on a site that was perfect for a 35t rough terrain crane. It went in perfectly in one shot! The 0.25 Yumbo (backhoe) was raised at the beginning of the month, the demolition work progressed, and the work was to lower the Yumbo. This time, we received help from Tanaka Heavy Equipment Industry. Thank you as always.

See photos and site details in detail
20ft sign container size
20ft container size

05

20ft sign container size

That's what I mean when I say it can be loaded with a fork! ? , No, that's not right, tell Kazuko Transport that it's impossible! I managed to load one unit with Unic, but the other one is heavier! What's more, I had heard about 20-foot dry containers, but when I was setting up the container trolley for the 20-foot container size I had made, it wouldn't fit! Plus, I didn't hear about taking it out of the building lol lol I had two forks, so that was a good thing. I was beaten. Apparently the customer directly above me wasn't shown anything either. After all, you should not work with someone who cannot confirm the details. I learned a lot too. I left, wondering what would happen to the person loading the truck if it was damaged so much.^_^

See photos and site details in detail
walkie lift
crab crane

06

walkie lift

For the second time on Saturday, I went to the site that had been cleared in the morning to participate. The machines were working, and it was extremely hot. Everyone did their best despite the heat ^_^And we were so disappointed that we were ahead of schedule. Thank you everyone. I almost fell over, but it was fun lol thank you.

See photos and site details in detail
Removal and transport work
Removal and transport work

07

Removal and transport work

The schedule for 2.5 days ended up being 4 days full due to additions etc. This is removal work. Everyone worked hard and finished it well. I was able to get help with the trestle stage and it went well ^ ^ Thank you.

See photos and site details in detail
Signboard renovation
Temporary construction work for signboard renovation

08

Signboard renovation

Temporary construction work for signboard renovation. The signboard is now beautiful ^ ^ Good. For two weeks in a row, we used temporary construction to raise and lower materials in order to raise and lower the roof. Thank you for finishing this safely.

See photos and site details in detail
Kyoei Transport
100R

10

Kyoei Transport

The tower crane was being dismantled in a fairly narrow space. The other day I was climbing backwards and had reached the bottom, so I finished 13R around noon. Thank you very much for today ^ ^

See photos and site details in detail
Kyoei Transport
100R

13

Kyoei Transport

In Akashi, we came to Kyoei Transport's 100R multi-level parking lot demolition site. We also look forward to your continued support in the new year. Everyone is working well and everything is going well. thank you.

See photos and site details in detail
Carrying in the electrical panel
high hand lift

14

Carrying in the electrical panel

The electrical panel was brought in. It's been a while since I've been there, so I didn't take many pictures lol I went up the stairs to the height full of Uniques (a mistake in my calculations lol), and I set the height of the stage to the entrance of the door at the landing, and thought I'd be able to catch it with my hand (also a mistake in my calculations), but I ended up getting it in with a roll lol Once I entered the door, I put it on a 3t long hand and went through the passage to the next gate. There will be a hurdle around 220H, which you will overcome by switching from a 3t long hand to a 1.5t small hand. After crossing it, it turns 90 degrees, and next there are three Φ65 pipes lying side by side. This was accomplished by putting a roller on top of the hand and the van and rolling it from hand to hand. Once you cross it, a platform will appear. The height of the pedestal installed earlier is 500H. This time, how about a short high hand lift that lifts 450H with 1t? I changed hands from the side and put it in the other way (well, I thought it would turn lol), so I turned it 180 degrees at the last minute. Then, I jacked it up with my high hand, and since it is 500H, it will arrive once I receive it ^ ^ Then, since it will exceed the height of the pedestal, I slide it vertically with a roller from side to side and into position. Then, raise it a little with the crowbar, bring the roller to the middle, take turns pulling it out, and land. When all that was left was to show the level, I was relieved of my role and was sent elsewhere. I enjoyed it. Now, how many hand lifts did you use to insert one board? Lol lol It was a hand lift festival ^ ^ And thank you very much for cleaning up and coming home ^ ^

See photos and site details in detail
Hiju Crane Co., Ltd.
100R

16

Hiju Crane Co., Ltd.

At the request of Hiju Crane, we relocated the machine ^ ^It was rare for us to have a press come to work. Thank you everyone ^ ^ There were other machines as well, but everything went as planned. thank you very much.

See photos and site details in detail
130t all terrain crane
high hand lift

17

130t all terrain crane

Today we were helped by a 130t all-terrain crane. The main thing was lifting a backhoe, but since it was in the afternoon, I couldn't take any pictures ^ ^ It seems that the KA-1300SL of Yasuho Crane Lease, which can often be seen on the TCL logo, came to see us ^ ^ Thank you very much.

See photos and site details in detail
loading crane
crab crane

18

loading crane

I'm a Uniq operator who hurriedly helped with the transport.^^It looks like we'll be moving to the installation site tomorrow. After I was excused from my role here, I went to Kyoto to support me ^ ^

See photos and site details in detail
Arita industry
Izumi Crane

19

Arita industry

At Arita Kogyo's site, Izumi Crane is working on building the wooden structure. The building is 50m deep and has been divided into two sections, and construction has begun on the remaining section. Although it is a one-story building, it is a very large wooden structure. Thank you for your continued support until the end.

See photos and site details in detail
Tyra Heavy Equipment Construction
Weight on 85R

20

Tyra Heavy Equipment Construction

Tyra Heavy Equipment Construction helped us with the construction. Will 85R need weights? Thank you for your continued support until the end.

See photos and site details in detail
crane
crane

21

crane

I'm on night shift. This is a transformer update. I was updating three transformers in the basement of a luxury condominium. Everyone came together to finish it off very well. thank you.

See photos and site details in detail
sakai crane
100t Rough Terrace Crane Hisatec Engineering Co., Ltd.

23

sakai crane

At Futaba Giken's site, we helped with the removal ^ ^ We also had Hiju Crane's 25R help, and we worked on Saturdays and Sundays. It seems things went better than planned, so we came back early today as well^ ^I'm glad it went well^ ^Our electric hand lift, walkie lift, and teppanyaki machine have also returned^ ^We'll be working hard at the site the day after tomorrow^ ^Thank you everyone for your hard work. thank you.

See photos and site details in detail
crane
crane

24

crane

Demolition work is being carried out steadily even in the extremely hot weather. We are entering the final stage. Construction will take approximately 3 weeks. The construction work will take more than three months, including the demolition of the building. Almost there. Thank you for your safety.

See photos and site details in detail
4t unic
4t unic

25

4t unic

I went to Mr. Landsburg to replace his paint machine. I decided to change the plan to a crab crane instead of a portal, took some serious measurements, and drew up a drawing to give it a try.It looked pretty good, so I decided to take on the challenge. Looks like it turned out better than I expected

See photos and site details in detail
sakai crane
100t Rough Terrace Crane Hisatec Engineering Co., Ltd.

26

sakai crane

He was in a busy area early in the morning and went to raise the backhoe onto the rooftop. 100R is here ^ ^ Please take a look ^ ^ Thank you as always.

See photos and site details in detail
4t unic
4t unic

28

4t unic

They went to install the items that had been delayed since the beginning of this year ^ ^ It was just 4t Unique. It seems like it was easy because there wasn't much fighting ^ ^ I guess I just put it there! Please don't rush into it ^ ^ Thank you for your hard work,

See photos and site details in detail
sakai crane
100t Rough Terrace Crane Hisatec Engineering Co., Ltd.

29

sakai crane

This is the 20R, which was saved by Sakai Crane.Although it is still a small machine, its size and performance are quite impressive, so I think it is a good machine^ ^Thank you^ ^We look forward to your continued support.

See photos and site details in detail
crab crane
crab crane

30

crab crane

A simple crab crane jib? A simplified version of the searcher hook. For now, it might be okay to lift 600kg lol. Let's move forward once we see improvements.

See photos and site details in detail
4t unic
4t unic

31

4t unic

They came to us after completing the construction work which took 2 months. Thanks to everyone's cooperation, we were able to complete the project, although there were many difficulties. I'm really grateful to everyone. The next construction will begin soon. The content is more difficult, but let's do it even better than this time. Thank you for your support.

See photos and site details in detail
Arita industry
100t Rough Terrace Crane Hisatec Engineering Co., Ltd.

32

Arita industry

At Arita Kogyo's site, we are helping Niyama Crane with the construction of a 25R wooden structure. The width was less than 10m and the depth was 50m, but they had to do the foundation work on the back half first, then move on to the front. That's amazing ^ ^ Thank you for letting me participate ^ ^ We look forward to your continued support.

See photos and site details in detail
1.5t electric hand lift
crab crane

33

1.5t electric hand lift

New friends have joined us ^ ^ 1.5t electric hand lift, and Hilti items ^ ^ and Aobeni have also been added. After making some changes to the electric hand lift, I will repaint it in Hisatec color. Thank you everyone for your continued support.

See photos and site details in detail
Mr. Shimaden
Mr. Shimaden

34

Mr. Shimaden

Please take a close look. This is a camera image from the jib ^ ^ It's a good shot. It's 13R though. Everyone went to install the signboards that Shimaden had made. It was completed very well ^ ^ Thank you for your hard work.

See photos and site details in detail
matsumoto industry
100t Rough Terrace Crane Hisatec Engineering Co., Ltd.

35

matsumoto industry

At Matsumoto Sangyo's site, we were helped by Sanwa Crane's rare 65t all-terrain crane. It is a Liebherr machine called LTM1065NX-2. It is a machine that can be expected to perform in the 100t class depending on how it is used^ ^This signboard weighed about 5t, which was lighter than expected^ ^Thank you as always, everyone.

See photos and site details in detail
Sanwa Crane
crab crane

36

Sanwa Crane

Sanwa Crane helped me. The working radius of modern cranes is outrageous. It looks like I was able to get 2t in 50m lol, that's amazing! Our 100R was also working hard from early in the morning ^ ^ Thank you as always.

See photos and site details in detail
100t Rough Terrace Crane Hisatec Engineering Co., Ltd.
100t Rough Terrace Crane Hisatec Engineering Co., Ltd.

37

100t Rough-Terrain Crane — Hisatec Engineering Co., Ltd.

I was dispatched for the first time to work for Tyra Heavy Equipment Construction ^ ^100R! thank you! It is said that the first appearance on a rainy day is auspicious. There is a word called ``furikomiru''. I would also like to thank Tyra Juki for moving this on this day. I wonder if I'll be able to run fast from now on lol Thank you everyone for your support.

See photos and site details in detail
100t Rough Terrace Crane Hisatec Engineering Co., Ltd.
100t Rough Terrace Crane Hisatec Engineering Co., Ltd.

38

100t Rough-Terrain Crane — Hisatec Engineering Co., Ltd.

They installed a signboard for a 100t rough terrain crane. We asked Hakko Corporation to take on the challenge. Thank you! I made something really cool! As for the painting, Maruei Painting worked very hard and did an amazing job. I had Maruei Painting do some amazing painting in Nara. And we had Hakko Corporation make a wonderful signboard. I am very grateful to all of you. There is still some bodywork left, but let's call it complete for now. Thanks to everyone, we were able to create a very beautiful 100t rough terrain crane. thank you!

See photos and site details in detail
100t Rough Terrace Crane Hisatec Engineering Co., Ltd.
100t Rough Terrace Crane Hisatec Engineering Co., Ltd.

39

100t Rough-Terrain Crane — Hisatec Engineering Co., Ltd.

I was able to operate the 100t rough terrain crane, too lol. This child's operator had gone to the site, so I learned how to use the crane computer for the first time in a long time in order to receive the containers my colleagues brought in. When I attached the sign, I lowered the jib that was holding it next to it, and started by raising it from the bottom to the side. I researched how to store the jib and was able to do it properly ^ ^ Then, I set it up for work and was able to hang the container as well ^ ^ There were tools inside, so it was heavy lol I was able to hang it at 100 tons lol Also, a light truck also came to the garage, so we had a matching design, so it was a lot of laughter ^ ^ We were able to do this because everyone was around us. I'll do my best, so let's all move forward together ^ ^ Thank you for your support.

See photos and site details in detail

CONTACT

Built Around Actual Site Conditions. We Recommend the Best Method.

Contact

PHOTO ARCHIVE

Photographs from the Current Website

All photographs published on the current HISATEC website have been carried over without cropping.

HISATEC photograph 1
HISATEC photograph 2
HISATEC photograph 3
HISATEC photograph 4
HISATEC photograph 5
HISATEC photograph 6
HISATEC photograph 7
HISATEC photograph 8
HISATEC photograph 9
HISATEC photograph 10
HISATEC photograph 11
HISATEC photograph 12
HISATEC photograph 13
HISATEC photograph 14
HISATEC photograph 15
HISATEC photograph 16
HISATEC photograph 17
HISATEC photograph 18
HISATEC photograph 19
HISATEC photograph 20
HISATEC photograph 21
HISATEC photograph 22
HISATEC photograph 23
HISATEC photograph 24
HISATEC photograph 25
HISATEC photograph 26
HISATEC photograph 27
HISATEC photograph 28
HISATEC photograph 29
HISATEC photograph 30
HISATEC photograph 31
HISATEC photograph 32
HISATEC photograph 33
HISATEC photograph 34
HISATEC photograph 35
HISATEC photograph 36
HISATEC photograph 37
HISATEC photograph 38
HISATEC photograph 39
HISATEC photograph 40
HISATEC photograph 41